Feed mill machinery from tonnes an hour

How the Feed mill tool turns capacity in tonnes an hour, hours run and pelleted share into bins, hammer mills, a mixer, pellet mills, a cooler and bagging lines.

By Site AdministratorUpdated 4 min read

A feed mill is rated in tonnes an hour, not tonnes a day, because the machinery has to deliver that rate while it is running. Behind the one figure sit intake, grinding, batching, mixing, pelleting, cooling, storage and bagging. The Feed mill tool takes five figures and lists each machine with a size, a quantity and the reason for it. You then enter your own rate against each line.

How the calculation works

The starting values are 10 tonnes an hour, 16 operating hours, 70% of the output pelleted, 12 ingredient bins and 10 days of raw material storage. The tool first works out:

  • Mill rate (kg/h) = capacity × 1000.
  • Pellet rate = mill rate × pelleted share ÷ 100.
  • Daily output = capacity × hours, in tonnes.

The lines then follow these rules:

  • Intake pit, elevator and drum sieve at twice the mill rate, so deliveries are not held.
  • Ingredient bins hold the storage days of daily output at 650 kg/m³, split over the number of bins you enter and rounded up to a stock size.
  • Hammer mills: one per 8 tonnes an hour, rounded up, each listed at the full mill rate.
  • Two batch weigh hoppers and one twin-shaft mixer, each at the mill rate ÷ 12 kg per batch, on the basis of twelve batches an hour.
  • A liquid addition skid at 3% of the mill rate.
  • Pellet mills: one per 10 tonnes an hour of pellet rate, rounded up, with a minimum of one. Cooler and crumbler at the pellet rate.
  • Four finished feed bins, each sized on half a day of output at 620 kg/m³ and rounded up to a stock size.
  • Two bagging lines at the mill rate, and dust control at 2% of the mill rate in m² of filter cloth.

A worked example

Take the starting values.

  • Mill rate = 10 × 1000 = 10,000 kg/h. Pellet rate = 10,000 × 0.70 = 7,000 kg/h. Daily output = 10 × 16 = 160 tonnes.
  • Intake = 10,000 × 2 = 20,000 kg/h.
  • Ingredient bins = 160,000 × 10 ÷ 12 = 133,333 kg each, which is 205.1 m³, shown as 250 m³ for each of 12.
  • Hammer mills = 10 ÷ 8 = 1.25, so 2 mills. Mixer and weigh hoppers = 10,000 ÷ 12 = 833 kg per batch. Liquid skid = 300 kg/h.
  • Pellet mills = 7,000 ÷ 10,000 = 0.7, so 1. Cooler and crumbler are listed at 7,000 kg/h.
  • Finished bins = 80,000 kg ÷ 620 = 129 m³, shown as 150 m³ for each of 4.
  • Dust control = 10,000 × 0.02 = 200 m² of cloth.

Now raise the capacity to 20 tonnes an hour. Hammer mills become 20 ÷ 8 = 2.5, so 3, and the pellet rate of 14,000 kg/h needs 14,000 ÷ 10,000 = 1.4, so 2 pellet mills.

Reading the result

Rounding drives the counts. At 10 tonnes an hour the plant needs 1.25 hammer mills and buys two, so there is spare grinding; at 16 tonnes an hour the same rule gives exactly two. The pelleted share changes only the pellet mill, cooler and crumbler. Set it to zero and those three lines stay in the list at minimum size instead of disappearing, so you can see what you are leaving out; for a mash-only plant, delete them from your quotation. Storage days change only the ingredient bins. Note that the finished bin size is calculated on half a day of output and then shown with a quantity of four, so check that four bins of that size is what you mean to buy.

What the tool assumes and leaves out

  • It prices nothing. You supply the rate for each line and no market prices are built in.
  • Eight tonnes an hour per hammer mill, ten per pellet mill, twelve batches an hour and 3% liquids are fixed. Machines of other makes may differ.
  • The number of weigh hoppers (2), mixers (1), finished bins (4) and bagging lines (2) is fixed, not calculated.
  • Not in the list: the building, bulk raw material silos beyond the ingredient bins, the boiler for the conditioner, molasses storage, the electrical substation and the laboratory. Extruded aqua feed is a different plant.
  • Motor power is not sized. For a hammer mill or mixer drive, use the motor and gearbox selection calculator.

Common mistakes

  • Entering tonnes a day in the capacity field. The field is tonnes an hour.
  • Using 24 hours for a plant that really runs two shifts, which understates the storage and finished bins.
  • Leaving the pelleted share at 70% for a mash plant and then pricing a pellet mill it will never use.
  • Setting the ingredient bin count lower than the number of raw materials in the formulation.
  • Treating the rounded bin size as a recommendation. It is a stock size above the calculated volume.