Dairy plant machinery from litres of milk a day

How the Dairy plant tool turns litres a day, operating hours, silo storage and pouch share into reception, chilling, silos, separator, pasteuriser, filling and CIP lines.

By Site AdministratorUpdated 3 min read

A dairy is sized by the milk it must handle in a day, but the machines are sized by the hour, and tankers arrive in two peaks. The Dairy plant tool takes five figures and lists the equipment from reception to filling, with a size, a quantity and the reason for each line. It does not price anything: you enter your own rate against every line.

How the calculation works

The starting values are 50,000 litres a day, 16 operating hours, stainless 304 for milk contact, 12 hours of silo storage and 70% of the milk filled into pouches. The tool first works out:

  • Hourly rate (litres/h) = litres a day ÷ operating hours.
  • Flow (m³/h) = hourly rate ÷ 1000.
  • Silo volume = litres × storage hours ÷ 24 ÷ 1000, in m³, split over 2 silos and rounded up to a stock size.

The lines then follow these rules:

  • Reception tank and weigher, and the plate chiller, at twice the flow, so tankers are not held.
  • Cream separator, homogeniser (two-stage, 200 bar) and HTST pasteuriser (72 °C for 15 seconds) at the flow.
  • Three processing tanks, each sized on four hours of flow and rounded up to a stock size.
  • Pouch fillers: hourly rate × pouch share, divided by 4,000 litres an hour per machine, rounded up, with a minimum of one.
  • A crate line at the full hourly rate.
  • A three-tank CIP system, each tank 1.5 × flow with a floor of 2 m³, rounded up.
  • Eight sanitary pumps at 1.5 × flow, and 500 m of tube whose bore is chosen for 1.5 m/s at that flow, rounded to a nominal size.

A worked example

Take the starting values.

  • Hourly rate = 50,000 ÷ 16 = 3,125 litres/h. Flow = 3.125 m³/h.
  • Reception and chiller = 3.125 × 2 = 6.3 m³/h (6.25 rounded).
  • Silo = 50,000 × 12 ÷ 24 ÷ 1000 = 25 m³; over 2 silos that is 12.5 m³ each, shown as 15 m³.
  • Separator, homogeniser and pasteuriser = 3.1 m³/h.
  • Processing tanks = 3.125 × 4 = 12.5 m³, shown as 15 m³ for each of 3.
  • Pouch filler = 3,125 × 0.70 = 2,188 litres/h; 2,188 ÷ 4,000 = 0.55, so 1 machine.
  • CIP = 3.125 × 1.5 = 4.7 m³, shown as 5 m³ per tank. Pumps = 4.7 m³/h.
  • Tube: 4.69 m³/h at 1.5 m/s needs a 33.2 mm bore, so NB 40 mm.

Now raise the milk to 200,000 litres a day. Flow becomes 12.5 m³/h, each silo 50 m³, the pouch load of 8,750 litres/h needs 8,750 ÷ 4,000 = 2.2, so 3 machines, and the tube bore of 66.5 mm moves up to NB 80 mm.

Reading the result

The hourly figures move in proportion to litres, but silos, tanks and machine counts move in steps. The operating hours matter more than they look: cutting 16 hours to 8 doubles the flow, and with it the separator, pasteuriser, pumps and tube bore. Silo storage changes only the two silos. The pouch share changes only the number of pouch fillers; the crate line is always sized on the whole hourly rate. The material choice changes the names on the lines and the stainless weight basis, not the sizes shown.

What the tool assumes and leaves out

  • It prices nothing and states no market prices. You supply the rate for each line.
  • The numbers of silos (2), processing tanks (3), pumps (8) and the 500 m of tube are fixed allowances, not calculated from your layout.
  • One separator, one homogeniser, one pasteuriser and one CIP set are listed whatever the size. A large dairy may need more than one.
  • Not in the list: the building, boiler and chilled-water plant, effluent treatment, generator, cold room, and cheese, yoghurt or powder lines.
  • Pump motor power is not sized. Use the pump head and power calculator for a duty, and the pipe size and pressure drop calculator for long runs.

Common mistakes

  • Entering the peak day rather than a normal day, which oversizes every line.
  • Using 24 hours for a plant that really stops between peaks, so every hourly figure comes out low.
  • Forgetting that reception and the chiller are listed at twice the flow.
  • Leaving the pouch share at 70% for a plant that sells only in cans or bulk.
  • Treating the 500 m of tube as a measured length. It is a starting allowance.

Try your own figures in the Dairy plant calculator.