Cold storage panels and refrigeration from tonnes held

How the Cold storage tool turns tonnage, chambers, room temperature, stacking density and daily intake into panels, doors, compressors, condensers, evaporators and standby power.

By Site AdministratorUpdated 5 min read

A cold store is bought by the tonnes it holds, but the refrigeration plant is sized by heat: what leaks in through the walls and what the warm produce brings in each day. The Cold storage tool takes five figures and lists the insulated envelope, the refrigeration plant, and the racking, controls and standby power, with a size, a quantity and the reason for each line. It does not price anything: you enter your own rate against every line, and it states no market prices.

How the calculation works

The starting values are 2,000 tonnes, 4 chambers, a room temperature of 2 °C, a stacking density of 320 kg/m³ and a daily intake of 5% of capacity. The tool first works out:

  • Stacked volume (m³) = tonnes × 1000 ÷ density, divided equally between the chambers.
  • Panel area: each chamber is treated as a box whose side is the cube root of its volume and whose height is 1.2 × that side. Area per chamber = 2 × side² (floor and roof) + 4 × side × 1.2 side (walls); the total is that times the number of chambers.
  • Frozen or chilled: a room at or below −10 °C is frozen. Panel thickness is 150 mm frozen and 100 mm chilled.
  • Transmission load (kW) = panel area × (35 − room temperature) × 0.24 ÷ 1000, or 0.16 for the thicker frozen panel. The 35 °C is the design ambient.
  • Product load (kW) = tonnes × intake% × 1000 kg × 3.4 kJ/kg·K × 12 K ÷ 86,400 s. That is the day's intake cooled 12 degrees over 24 hours.
  • Refrigeration duty (kW) = (transmission + product) × 1.35, with a floor of 5 kW. The 35% covers lights, fans, doors and people.

The lines then follow these rules:

  • Panels at the total area, an insulated floor of volume ÷ (1.2 × side), two doors per chamber, and one dock bay per two chambers, rounded up.
  • Compressor packs: duty ÷ 120 kW, rounded up, with a minimum of two; two-stage when frozen. Condensers at 1.3 × duty, one per 200 kW of duty.
  • Two evaporators per chamber, each line sized at duty ÷ chambers. Refrigerant piping at 120 m per chamber. Two receivers of duty ÷ 90 m³, floor 1 m³, rounded up.
  • Pallet racking at 900 kg a position, a control system for the chambers, and a standby generator at 1.6 × duty in kVA.

A worked example

Take the starting values.

  • Volume = 2,000 × 1000 ÷ 320 = 6,250 m³; 1,563 m³ per chamber. Side = ∛1,563 = 11.6 m.
  • Panel area = 4 × (2 × 11.6² + 4 × 11.6 × 13.9) = 3,663 m², 100 mm thick. Floor = 6,250 ÷ (11.6 × 1.2) = 449 m².
  • Transmission = 3,663 × 33 × 0.24 ÷ 1000 = 29 kW.
  • Product = 2,000 × 0.05 × 1000 × 3.4 × 12 ÷ 86,400 = 47 kW.
  • Duty = (29 + 47) × 1.35 = 103 kW. Compressors: 103 ÷ 120 = 0.9, so the minimum of 2 packs. Condenser = 134 kW rejected, 1 unit. Evaporators = 103 ÷ 4 = 26 kW each, 8 units.
  • Doors = 8; dock bays = 2; piping = 480 m; receivers = 103 ÷ 90 = 1.14 m³, shown as 1.5 m³, 2 vessels.
  • Racking = 2,000,000 ÷ 900 = 2,222 pallet positions. Generator = 103 × 1.6 = 165 kVA.

Now set the room to −18 °C. The panels become 150 mm, the doors get heated frames, the floor line calls for underfloor heating, and the compressors go two-stage. Transmission = 3,663 × 53 × 0.16 ÷ 1000 = 31 kW, so the duty is (31 + 47) × 1.35 = 106 kW and the generator 169 kVA. Keep 2 °C but cut the intake to 1% instead: the product load falls to 9 kW and the duty to 52 kW, with the generator at 83 kVA.

Reading the result

On a store taking in 5% a day the product load is larger than the transmission, so the daily intake moves the compressors more than the temperature does. Freezing adds only a few kilowatts of duty because the thicker panel offsets the wider temperature difference; what it changes is the panel, floor, door and compressor specification. The number of chambers changes the doors, evaporators and piping, and slightly raises the panel area, since four small boxes have more surface than one large one. Density changes only the building: denser stacking means less panel, less floor and less transmission. Racking depends on tonnage alone.

What the tool assumes and leaves out

  • It prices nothing and states no market prices. You supply the rate for each line.
  • The envelope is a near cube per chamber. A long, low shed has more surface and more transmission than the figure shown.
  • The 35 °C ambient, the 12 K pull-down, the 3.4 kJ/kg·K specific heat and the 35% margin are fixed. Fruit arriving at 30 °C into a 2 °C room cools far more than 12 degrees, so pull-down with pre-cooling may need separate plant.
  • Door counts (2 per chamber), evaporators (2 per chamber), piping (120 m per chamber) and receivers (2) are fixed allowances.
  • Not in the list: the building shell and foundations, the electrical supply to the plant room, fire protection, forklifts and handling equipment, and the land.

Common mistakes

  • Entering the peak intake day as the daily intake, which oversizes the compressors for the whole year.
  • Entering 0% intake for a store that is loaded over a few weeks in season.
  • Treating the panel area as a measured take-off. It comes from an idealised box.
  • Setting −18 °C without allowing for the underfloor heating and heated door frames the list adds.
  • Reading the generator as the compressor motor size. It is 1.6 × the refrigeration duty in kVA, to carry the whole plant.

Try your own figures in the Cold storage calculator.