Water treatment and RO plant machinery from cubic metres an hour

How the Water treatment and RO plant tool turns permeate flow, operating hours, feed TDS, recovery and storage hours into filters, membranes, pumps and tanks.

By Site AdministratorUpdated 4 min read

A water plant is bought by the cubic metres an hour of treated water it must deliver, but almost every piece of equipment upstream of the membranes is sized on the raw water going in, which is always more. The Water treatment and RO plant tool takes five figures and lists the pre-treatment, the reverse osmosis section and the post-treatment and storage, with a size, a quantity and the reason for each line. It does not price anything: you enter your own rate against every line, and it states no market prices.

How the calculation works

The starting values are 25 m³/h of permeate, 20 operating hours a day, a feed of 1,500 mg/litre total dissolved solids (TDS), 70% recovery and 8 hours of treated water storage. The tool first works out:

  • Feed (m³/h) = permeate ÷ (recovery ÷ 100). This is the raw water the pre-treatment and the high pressure pump must handle.
  • Reject (m³/h) = feed − permeate.
  • Design flux: 20 litres per m² per hour for a feed up to 2,500 mg/l, 17 up to 5,000 mg/l, and 14 above that. A saltier feed is pushed harder and fouls faster, so the flux comes down.
  • Membrane area (m²) = permeate × 1000 ÷ flux. Elements = area ÷ 37 m² per 8040 element, rounded up; pressure vessels = elements ÷ 6, rounded up.
  • Storage hours = the larger of the hours you asked for and the idle hours (24 − operating hours). Storage volume = permeate × storage hours, split over 2 tanks and rounded up to a stock size.

The lines then follow these rules:

  • A raw water tank holding two hours of feed, rounded up to a stock size.
  • Two multigrade sand filters and two activated carbon filters at the feed flow, and one 5 micron cartridge housing.
  • Two dosing skids (antiscalant and sodium metabisulphite) at 0.02% of the feed flow.
  • Two high pressure pumps (duty and standby) at the feed flow, rated 15 bar up to 5,000 mg/l and 25 bar above.
  • One RO skid at the permeate flow, and a CIP system of 0.6 m³ per pressure vessel with a floor of 1 m³, rounded up.
  • A UV steriliser and a remineralisation set at the permeate flow, two distribution pumps at 1.5 × permeate, and a reject line at the reject flow.

A worked example

Take the starting values.

  • Feed = 25 ÷ 0.70 = 35.7 m³/h. Reject = 35.7 − 25 = 10.7 m³/h, which is 30% of the feed.
  • Raw water tank = 35.7 × 2 = 71.4 m³, shown as 75 m³.
  • Sand filters, carbon filters, cartridge housing and high pressure pumps = 35.7 m³/h; the pumps at 15 bar. Dosing skids = 35.7 × 0.0002 = 0.007 m³/h.
  • Flux at 1,500 mg/l = 20. Area = 25 × 1000 ÷ 20 = 1,250 m². Elements = 1,250 ÷ 37 = 33.8, so 34. Vessels = 34 ÷ 6 = 5.7, so 6.
  • CIP = 6 × 0.6 = 3.6 m³, shown as 4 m³.
  • Idle hours = 24 − 20 = 4; storage hours = max(8, 4) = 8. Storage = 25 × 8 = 200 m³, so 2 tanks of 100 m³.
  • Distribution pumps = 25 × 1.5 = 37.5 m³/h.

Now raise the TDS to 6,000 mg/l and cut the running time to 12 hours. The flux falls to 14, so the area is 1,786 m², 49 elements in 9 vessels, and the pumps are rated 25 bar. The plant is idle 12 hours a day, so storage rises to 12 hours: 300 m³, or 2 tanks of 150 m³. The CIP becomes 9 × 0.6 = 5.4 m³, shown as 6 m³. Lower the recovery to 50% instead, and feed becomes 50 m³/h with 25 m³/h of reject, while the membrane count does not change.

Reading the result

Permeate sets the membrane area and the post-treatment. Recovery sets everything upstream: at 70% every cubic metre of product needs 1.43 m³ of feed, at 50% it needs 2. Membranes move in steps of one element and one six-element vessel, so a small change in flow may change nothing or add a whole vessel. The storage line reads the operating hours: a plant running 20 hours against a 24-hour draw is short 4 hours a day whatever buffer you typed, and the basis text tells you when the idle hours took over. The pump pressure and the flux change only at the 2,500 and 5,000 mg/l thresholds.

What the tool assumes and leaves out

  • It prices nothing and states no market prices. You supply the rate for each line.
  • The flux figures, the 37 m² element and six elements a vessel are typical brackish-water values, not a membrane projection. Run the supplier's software before buying membranes.
  • The counts of filters (2), dosing skids (2), pumps (2) and storage tanks (2) are fixed allowances.
  • Above about 10,000 mg/l the pressures, membranes and materials change; the tool was built for brackish water.
  • Not in the list: the bore well or raw supply, civil work and plant room, electrical supply, brine disposal beyond the discharge line, ozonation or bottling.
  • Pump motor power is not sized. Use the pump head and power calculator for a duty, and the pipe size and pressure drop calculator for long lines.

Common mistakes

  • Entering raw water in as the flow. The tool wants treated water out; it works the feed out itself.
  • Entering 24 hours for a plant that stops for backwash and CIP, which hides the storage shortfall.
  • Reading the storage as the buffer you typed when the idle hours were larger.
  • Leaving the carbon filter and bisulphite dosing out to save money on a chlorinated supply. Chlorine destroys a polyamide membrane in hours.
  • Forgetting the reject: 30% of the feed at the default settings has to go somewhere legal.