Unit mistakes that cost money on machinery quotations
Eight unit mix-ups that regularly turn up in machinery quotations, with worked numbers, and a few simple habits that catch them before an order is placed.
A machinery quotation passes through many hands: the designer, the supplier, the fabricator and the buyer. Each may work in different units, and a quiet mix-up between two similar-looking units can mean a pump that is too small or a motor that does not match the supply. This article lists the mix-ups that turn up most often and some habits that catch them early.
Why unit errors survive so long
Most unit mistakes are not arithmetic errors. The number is correct in one unit and is then read in another. A quotation that says "75 hp" or "10 bar" looks complete, yet each of those has more than one possible meaning. Because the figures look reasonable, nobody questions them until the machine is on site.
Eight pairs to watch
Pair | What can go wrong |
|---|---|
kW and hp | 75 kW is about 100.6 mechanical hp but about 102.0 metric hp (PS). Three different horsepower figures exist, so ask which one. |
bar and kgf/cm² | 10 kgf/cm² is 9.81 bar. One bar is about 14.5 psi. |
US and imperial gallon | 100 US gallons is 378.5 litres; 100 imperial gallons is 454.6 litres, about 20% more. |
Tonne and short ton | 10 short tons is 9.07 tonnes. A long ton is about 1.016 tonnes. |
Gauge and absolute pressure | 1 bar gauge is about 2.01 bar absolute, because the atmosphere adds about 1.013 bar. |
kW and kVA | 100 kVA at a power factor of 0.8 delivers 80 kW, not 100 kW. |
Tonnes per day and per hour | 120 tonnes per day is 5 t/h if the plant runs 24 hours, but 6 t/h if it runs only 20 hours. |
m³/h and L/min | 1 m³/h is about 16.7 L/min, so 50 m³/h is about 833 L/min. |
Pipe sizes need a separate warning. A nominal 4 inch pipe is a name for a size, not a measurement: its outside diameter is 114.3 mm, not 101.6 mm. Always check whether a figure is nominal, inside or outside diameter.
Habits that catch mistakes
- Write the unit beside every number. A bare "50" in a quotation is a question, not an answer.
- Say whether a pressure is gauge or absolute and whether a capacity is per hour of running time or per day of 24 hours.
- Convert once, in one place, and keep the original figure in brackets so a reader can trace it.
- Round only at the end. Rounding 0.98 to 1 before multiplying by a large flow hides a real difference.
- Check the order of magnitude. A 5 kW pump quoted for a duty that needs 50 kW should look wrong at a glance.
- Compare two quotations unit by unit. A price that looks lower sometimes belongs to a smaller machine.
Practical takeaways
- Ask every supplier which horsepower, gallon, ton and pressure reference they mean.
- Put electrical ratings in kW and kVA, with the power factor and supply voltage.
- Keep one agreed unit set for the whole project and state it on the first page.
- Re-check any figure that changed units between drawing, datasheet and quotation.
For quick conversions with every unit shown side by side, use the engineering unit converter. Always confirm final values against the supplier's datasheet and local standards.