How the Cooking oil and ghee mill machinery tool turns a refinery's daily tonnage into tanks, vessels, filters, pumps and pipe, and how its rate column is filled.

By Site AdministratorUpdated 5 min read

Before anyone asks a fabricator to price an edible-oil refinery, someone has to list what the plant contains and how big each item is. The Cooking oil and ghee mill machinery tool does that take-off from the tonnage of oil the refinery puts through in a day. It lists tanks, process vessels, separators, filter presses, pumps, pipe and valves, each with a size, a quantity and the basis it was sized on, and it leaves a rate column for pricing.

How the calculation works

Everything starts from the oil flow. With throughput T in tonnes a day, operating hours H and oil density ρ (910 kg/m³ by default):

  • Daily volume (m³/day) = T × 1000 ÷ ρ, and line flow (m³/h) = daily volume ÷ H.
  • Storage: crude = daily volume × crude days, refined = daily volume × refined days. Each is split over the number of tanks you choose (two by default) and rounded up to a size a fabricator builds.
  • Process vessels: volume = line flow × residence time ÷ 0.75, so a quarter of each vessel is freeboard, then rounded up on the tool's ladder of sizes (1, 1.5, 2, 2.5, 3, 4, 5, 6, 7.5, 10, 12, 15 m³ and so on). The residence times are 20 minutes for the acid mixer and the neutraliser, 10 minutes for each of two wash mixers, 30 minutes for the vacuum dryer and the bleacher, 90 minutes for the deodoriser, 4 hours for each of two day tanks and 8 hours for the winterising tanks.
  • Hydrogenation: two converters, sized on the hardened share of the flow only, at 2 hours a batch, so one charges while the other reacts.
  • Filters: bleached oil at 120 litres per m² of cloth per hour and winterised oil at 70, with a minimum of 2 m².
  • Pumps and pipe: transfer pumps at twice line flow, and a bore chosen so that flow runs at about 1.5 m/s, rounded up to the next nominal bore.

A worked example

Take the starting values: 50 tonnes a day, 22 operating hours, SS 304 for oil-contact parts, 40% hardened for ghee, 7 days of crude and 5 days of refined storage in two tanks each, 0.8% bleaching earth and 910 kg/m³.

  • Daily volume = 50 × 1000 ÷ 910 = 54.9 m³, and line flow = 54.9 ÷ 22 = 2.5 m³/h.
  • Crude storage = 54.9 × 7 = 384.6 m³, or 192.3 m³ per tank, so two 200 m³ mild steel tanks. Refined storage = 54.9 × 5 = 274.7 m³, so two tanks of 150 m³.
  • Neutraliser = 2.5 × 20/60 ÷ 0.75 = 1.11 m³, so 1.5 m³. Bleacher = 2.5 × 0.5 ÷ 0.75 = 1.67 m³, so 2 m³. Deodoriser = 2.5 × 1.5 ÷ 0.75 = 5.0 m³, so 5 m³.
  • Hardened flow = 40% of 2.5 = 1.0 m³/h, so each converter is 1.0 × 2 ÷ 0.75 = 2.7 m³, rounded up to 3 m³.
  • Bleaching earth = 2,273 kg/h × 22 h × 0.8% = 400 kg a day. A week of it at 600 kg/m³ is 4.7 m³, so a 5 m³ silo. The bleached-oil filter press needs 2.5 × 1000 ÷ 120 = 20.8 m² of cloth.
  • Transfer pumps run at 5.0 m³/h. At 1.5 m/s that needs a 34 mm bore, so the pipe is NB 40.

Doubling the plant to 100 tonnes a day moves the neutraliser to 2.5 m³, the deodoriser to 10 m³, the pipe to NB 50 and each crude tank to 400 m³.

Reading the result

Each line shows what the item is, its size, how many and, in small print, the basis it was sized on, so a figure that does not suit your process is easy to spot and change. Oil-contact lines take the grade you chose. Crude, gum and soapstock tanks stay mild steel, while the deodoriser, the hydrogenation converters and the acid splitting tanks are always SS 316 because of the heat and acid they see. A unit with more than about 15 tonnes of steel is marked site-erected, because it cannot travel by road in one piece.

The tool holds no price list. In "Estimate for me" mode it fills each rate from two figures for your own market: a rate per kg of fabricated mild steel and a rate per day of skilled labour. Each line's rate = steel or steel-equivalent mass × your steel rate (× 3.2 for stainless) + install days × your labour rate. The starting values in those two fields are placeholders only, so replace them with figures from your own recent invoices. In "Enter my own" mode you type every rate yourself, and the total counts only the lines that have one.

What the tool assumes and leaves out

  • It sizes a continuous refinery. The residence times are ordinary starting figures; if your process licensor gives different ones, use theirs.
  • Throughput is oil through the refinery, not seed through an expeller. Seed preparation and pressing are not included.
  • Pipe is a fixed allowance of 900 m with 90 valves. It is not a route, so replace it with a take-off from your layout.
  • Steam generation, electricals, instrumentation, structural steel, civil work and buildings are not listed.
  • No figure is a market price. Every estimate comes from your two anchors, so check it against supplier offers before you issue a quotation.

Common mistakes

  • Entering the seed tonnage of the expeller instead of the oil going into the refinery.
  • Entering 24 operating hours for a plant that stops every day for cleaning. Fewer hours mean a higher hourly flow and larger vessels.
  • Leaving the hardened share at 40% when the plant only bottles liquid oil. That adds converters, a hydrogen plant and a ghee chilling line you do not need, so set it low.
  • Choosing mild steel for refined-oil contact parts just to lower the total.
  • Sending the 900 m pipe allowance to a client as if it had been measured.
  • Quoting the estimated rates without first replacing the two anchors with your own figures.

Run your own plant in the Cooking oil and ghee mill machinery tool. To check the plate for a single tank use the MS and SS plate calculator, and for a transfer pump's motor the pump head and power calculator.

Keep reading