Runs in your browser
Soap & detergent plant
Enter the soap and detergent the factory makes in a day. The list below is what that implies — saponification, vacuum dryer, amalgamator, mills, plodder, stamper and the detergent spray tower — with a rate column you fill in yourself.
Your figures
Finishing lines run two shifts; the saponification section is continuous.
Set to zero for a soap-only plant.
Toilet soap needs milling and a vacuum plodder; laundry soap does not.
Material take-off
What to buy, at what size, and how many — worked out from the figures above.
Every line is estimated from those two figures: its steel — or steel-equivalent — mass at the steel rate, stainless at 3.2×, plus its install days at the labour rate. There is no price feed behind this, so the two anchors are seeded from typical Pakistan figures as of September 2026 and are yours to correct. Type over any individual rate and yours is used instead.
Saponification & drying
| Material | Size | No. | Total weight | Rate | Amount |
|---|---|---|---|---|---|
| Continuous saponification reactor, SS 316Oil and caustic, with the neat soap separated from lyeRate from 3,600 kg stainless-equivalent + 12 days labour — Reactor, mixer, separator and dosing | 1,000 kg/h2.4 t each | 1reactor | 2.4t | estimated | 4,638,000 |
| Caustic and brine preparationLye and brine made up and held for the reactorRate from 1,100 kg stainless-equivalent + 4 days labour — Tanks, agitators, dosing pumps and lines | 20 m³ | 2tank | — | estimated | 2,836,000 |
| Vacuum spray dryer for neat soapNeat soap at about 30% moisture down to 12% as noodlesRate from 5,200 kg stainless-equivalent + 14 days labour — Atomiser, drying chamber, vacuum set and noodle plodder | 1,000 kg/h | 1unit | — | estimated | 6,691,000 |
Continuous saponification reactor, SS 316
Oil and caustic, with the neat soap separated from lye
Rate from 3,600 kg stainless-equivalent + 12 days labour — Reactor, mixer, separator and dosing- Size
- 1,000 kg/h · 2.4 t each
- No.
- 1reactor
- Total weight
- 2.4 t
- Rate(estimated)
- Amount
- ₨ 4,638,000
Caustic and brine preparation
Lye and brine made up and held for the reactor
Rate from 1,100 kg stainless-equivalent + 4 days labour — Tanks, agitators, dosing pumps and lines- Size
- 20 m³
- No.
- 2tank
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 2,836,000
Vacuum spray dryer for neat soap
Neat soap at about 30% moisture down to 12% as noodles
Rate from 5,200 kg stainless-equivalent + 14 days labour — Atomiser, drying chamber, vacuum set and noodle plodder- Size
- 1,000 kg/h
- No.
- 1unit
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 6,691,000
Finishing
| Material | Size | No. | Total weight | Rate | Amount |
|---|---|---|---|---|---|
| Amalgamator / mixer for additivesPerfume, colour, titanium dioxide and preservative into the noodlesRate from 1,900 kg stainless-equivalent + 4 days labour — Trough, paddles, drive and dosing | 1,000 kg/h | 1unit | — | estimated | 2,442,000 |
| Three-roll refiner mill40% toilet soap, which has to be milled to disperse the perfumeRate from 2,400 kg + 5 days labour — Chilled rolls, frame, scraper and drive | 400 kg/h | 1mill | — | estimated | 972,500 |
| Duplex vacuum plodderExtrudes a continuous bar free of trapped airRate from 4,000 kg stainless-equivalent + 8 days labour — Two barrels, vacuum chamber, cone and nozzle | 1,000 kg/h | 1plodder | — | estimated | 5,140,000 |
| Bar cutter and soap stamping machineCut to length, then stamped to shape and brandedRate from 1,800 kg + 5 days labour — Cutter, conveyor, stamper dies and chiller | 1,000 kg/h | 2machine | — | estimated | 1,465,000 |
Amalgamator / mixer for additives
Perfume, colour, titanium dioxide and preservative into the noodles
Rate from 1,900 kg stainless-equivalent + 4 days labour — Trough, paddles, drive and dosing- Size
- 1,000 kg/h
- No.
- 1unit
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 2,442,000
Three-roll refiner mill
40% toilet soap, which has to be milled to disperse the perfume
Rate from 2,400 kg + 5 days labour — Chilled rolls, frame, scraper and drive- Size
- 400 kg/h
- No.
- 1mill
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 972,500
Duplex vacuum plodder
Extrudes a continuous bar free of trapped air
Rate from 4,000 kg stainless-equivalent + 8 days labour — Two barrels, vacuum chamber, cone and nozzle- Size
- 1,000 kg/h
- No.
- 1plodder
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 5,140,000
Bar cutter and soap stamping machine
Cut to length, then stamped to shape and branded
Rate from 1,800 kg + 5 days labour — Cutter, conveyor, stamper dies and chiller- Size
- 1,000 kg/h
- No.
- 2machine
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 1,465,000
Detergent powder
| Material | Size | No. | Total weight | Rate | Amount |
|---|---|---|---|---|---|
| Detergent slurry preparation, crutcherSulphonic acid, caustic, builders and water into a slurryRate from 2,100 kg stainless-equivalent + 6 days labour — Vessel, agitator, jacket and dosing | 750 kg/h | 2crutcher | — | estimated | 5,406,000 |
| Spray drying tower with HP pumpSlurry atomised into hot air, falling out as hollow beadsRate from 10,800 kg + 25 days labour — Tower shell, nozzles, HP pump, air heater and cyclones | 750 kg/h8.3 t each | 1tower | 8.3t | estimated | 4,382,500 |
| Post-dosing and perfuming drumEnzymes and perfume added after drying, where heat would destroy themRate from 1,550 kg + 4 days labour — Rotating drum, spray bars and dosing | 750 kg/h | 1unit | — | estimated | 630,000 |
Detergent slurry preparation, crutcher
Sulphonic acid, caustic, builders and water into a slurry
Rate from 2,100 kg stainless-equivalent + 6 days labour — Vessel, agitator, jacket and dosing- Size
- 750 kg/h
- No.
- 2crutcher
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 5,406,000
Spray drying tower with HP pump
Slurry atomised into hot air, falling out as hollow beads
Rate from 10,800 kg + 25 days labour — Tower shell, nozzles, HP pump, air heater and cyclones- Size
- 750 kg/h · 8.3 t each
- No.
- 1tower
- Total weight
- 8.3 t
- Rate(estimated)
- Amount
- ₨ 4,382,500
Post-dosing and perfuming drum
Enzymes and perfume added after drying, where heat would destroy them
Rate from 1,550 kg + 4 days labour — Rotating drum, spray bars and dosing- Size
- 750 kg/h
- No.
- 1unit
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 630,000
Packing & utilities
| Material | Size | No. | Total weight | Rate | Amount |
|---|---|---|---|---|---|
| Soap wrapping and cartoning lineWrap, carton and shrink for despatchRate from 2,000 kg + 6 days labour — Wrapper, cartoner, conveyor and coder | 1,000 kg/h | 2line | — | estimated | 1,630,000 |
| Powder filling and pouch lineAuger filler into pouches or cartonsRate from 1,900 kg + 6 days labour — Auger filler, form-fill-seal and coder | 750 kg/h | 2line | — | estimated | 1,550,000 |
| Steam, vacuum and chilled water connectionsHeaders and take-offs from the boiler house to each machineRate from 3,000 kg + 14 days labour — Headers, traps, valves, pipework and insulation | plant-wide | 1set | — | estimated | 1,235,000 |
Soap wrapping and cartoning line
Wrap, carton and shrink for despatch
Rate from 2,000 kg + 6 days labour — Wrapper, cartoner, conveyor and coder- Size
- 1,000 kg/h
- No.
- 2line
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 1,630,000
Powder filling and pouch line
Auger filler into pouches or cartons
Rate from 1,900 kg + 6 days labour — Auger filler, form-fill-seal and coder- Size
- 750 kg/h
- No.
- 2line
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 1,550,000
Steam, vacuum and chilled water connections
Headers and take-offs from the boiler house to each machine
Rate from 3,000 kg + 14 days labour — Headers, traps, valves, pipework and insulation- Size
- plant-wide
- No.
- 1set
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 1,235,000
Material
₨ 38,668,000
10.8 t of steel to fabricate
Labour
₨ 350,000
140 days at ₨ 2,500 a day
Quotation total
₨ 39,018,000PKR
13 of 13 lines priced
10.75 t is fabricated steel only. 11 bought-in lines — pumps, machines, proprietary units — are priced but carry no steel weight of ours, and show a dash in the weight column.