Runs in your browser
Flour mill machinery
Enter the wheat the mill grinds and the extraction you expect. The list below is what that implies — cleaning, tempering bins, roll length, sifters and packing — with a rate column you fill in yourself.
Your figures
Clean wheat to the first break, not wheat received.
Roller mills run continuously between cleaning shifts.
Flour out as a share of wheat in. The balance is bran and shorts.
Flour is bagged out quickly; bins hold hours, not weeks.
Material take-off
What to buy, at what size, and how many — worked out from the figures above.
Every line is estimated from those two figures: its steel — or steel-equivalent — mass at the steel rate, stainless at 3.2×, plus its install days at the labour rate. There is no price feed behind this, so the two anchors are seeded from typical Pakistan figures as of September 2026 and are yours to correct. Type over any individual rate and yours is used instead.
Intake & cleaning
| Material | Size | No. | Total weight | Rate | Amount |
|---|---|---|---|---|---|
| Intake hopper, elevator and pre-cleanerIntake runs at twice the milling rate so trucks are not heldRate from 4,275 kg + 6 days labour — Hopper, chain conveyor, elevator and drum sieve | 12,500 kg/h | 1set | — | estimated | 1,725,000 |
| Destoner and gravity separatorStones and mud balls out before the rollsRate from 2,025 kg + 3 days labour — Deck, fan and drive | 6,250 kg/h | 1unit | — | estimated | 817,500 |
| Scourer and aspirator with magnetsSurface dirt and beeswing off the grainRate from 2,350 kg + 3 days labour — Rotor, screen basket and aspiration | 6,250 kg/h | 2unit | — | estimated | 1,895,000 |
| Dampener and tempering bins, MS24 hours of tempering across three bins at 780 kg/m³Rate from 9,073 kg + 6 days labour — Hopper-bottom bin with water dosing and mixer | 200 m³7.6 t each | 3bin | 22.7t | estimated | 10,932,996 |
Intake hopper, elevator and pre-cleaner
Intake runs at twice the milling rate so trucks are not held
Rate from 4,275 kg + 6 days labour — Hopper, chain conveyor, elevator and drum sieve- Size
- 12,500 kg/h
- No.
- 1set
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 1,725,000
Destoner and gravity separator
Stones and mud balls out before the rolls
Rate from 2,025 kg + 3 days labour — Deck, fan and drive- Size
- 6,250 kg/h
- No.
- 1unit
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 817,500
Scourer and aspirator with magnets
Surface dirt and beeswing off the grain
Rate from 2,350 kg + 3 days labour — Rotor, screen basket and aspiration- Size
- 6,250 kg/h
- No.
- 2unit
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 1,895,000
Dampener and tempering bins, MS
24 hours of tempering across three bins at 780 kg/m³
Rate from 9,073 kg + 6 days labour — Hopper-bottom bin with water dosing and mixer- Size
- 200 m³ · 7.6 t each
- No.
- 3bin
- Total weight
- 22.7 t
- Rate(estimated)
- Amount
- ₨ 10,932,996
Milling
| Material | Size | No. | Total weight | Rate | Amount |
|---|---|---|---|---|---|
| Roller mill stand, double, 1000 mm11 mm of roll per tonne of wheat per 24 h, across break and reductionRate from 3,200 kg + 4 days labour — Chilled rolls, feeder, drive and frame | 1,650 mm roll total | 2stand | — | estimated | 2,580,000 |
| Plansifter, multi-sectionOne per 100 tonnes a dayRate from 2,800 kg + 5 days labour — Sieve stack, balance weights and drive | 6,250 kg/h | 2sifter | — | estimated | 2,265,000 |
| PurifierSemolina purification on the middlings streamsRate from 1,400 kg + 3 days labour — Sieve deck, aspiration and drive | 1,563 kg/h | 3unit | — | estimated | 1,702,500 |
| Bran finisher and vibro finisherRecovers flour still clinging to the branRate from 1,100 kg + 2 days labour — Beater rotor, screen and drive | 1,500 kg/h | 2unit | — | estimated | 890,000 |
Roller mill stand, double, 1000 mm
11 mm of roll per tonne of wheat per 24 h, across break and reduction
Rate from 3,200 kg + 4 days labour — Chilled rolls, feeder, drive and frame- Size
- 1,650 mm roll total
- No.
- 2stand
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 2,580,000
Plansifter, multi-section
One per 100 tonnes a day
Rate from 2,800 kg + 5 days labour — Sieve stack, balance weights and drive- Size
- 6,250 kg/h
- No.
- 2sifter
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 2,265,000
Purifier
Semolina purification on the middlings streams
Rate from 1,400 kg + 3 days labour — Sieve deck, aspiration and drive- Size
- 1,563 kg/h
- No.
- 3unit
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 1,702,500
Bran finisher and vibro finisher
Recovers flour still clinging to the bran
Rate from 1,100 kg + 2 days labour — Beater rotor, screen and drive- Size
- 1,500 kg/h
- No.
- 2unit
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 890,000
Pneumatics & handling
| Material | Size | No. | Total weight | Rate | Amount |
|---|---|---|---|---|---|
| Pneumatic conveying and aspiration systemLifts every stream between stands, sifters and binsRate from 8,600 kg + 14 days labour — Fans, cyclones, airlocks and ducting | 8,125 kg/h conveyed | 1system | — | estimated | 3,475,000 |
| Bag filter for dust collectionFlour dust is an explosion risk as well as a lossRate from 1,650 kg + 4 days labour — Housing, bags, cages and reverse-jet | 125 m² cloth | 2filter | — | estimated | 1,340,000 |
Pneumatic conveying and aspiration system
Lifts every stream between stands, sifters and bins
Rate from 8,600 kg + 14 days labour — Fans, cyclones, airlocks and ducting- Size
- 8,125 kg/h conveyed
- No.
- 1system
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 3,475,000
Bag filter for dust collection
Flour dust is an explosion risk as well as a loss
Rate from 1,650 kg + 4 days labour — Housing, bags, cages and reverse-jet- Size
- 125 m² cloth
- No.
- 2filter
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 1,340,000
Storage & packing
| Material | Size | No. | Total weight | Rate | Amount |
|---|---|---|---|---|---|
| Wheat silo, MS20 days of wheat at 780 kg/m³, over two silosRate from 56,855 kg + 10 days labour — Silo with hopper bottom, ladder, level and aeration | 2000 m³42.1 t eachsite-erected | 2silo | 84.2t | estimated | 45,533,838 |
| Flour bin, MS3 days of flour at 550 kg/m³, over four binsRate from 9,451 kg + 5 days labour — Bin with discharge screw and level | 200 m³7.6 t each | 4bin | 30.2t | estimated | 15,172,216 |
| Bagging and stitching lineWeigh, fill, stitch and conveyRate from 1,600 kg + 5 days labour — Weigher, bagger, stitcher and conveyor | 4,750 kg/h | 2line | — | estimated | 1,305,000 |
Wheat silo, MS
20 days of wheat at 780 kg/m³, over two silos
Rate from 56,855 kg + 10 days labour — Silo with hopper bottom, ladder, level and aeration- Size
- 2000 m³ · 42.1 t eachsite-erected
- No.
- 2silo
- Total weight
- 84.2 t
- Rate(estimated)
- Amount
- ₨ 45,533,838
Flour bin, MS
3 days of flour at 550 kg/m³, over four bins
Rate from 9,451 kg + 5 days labour — Bin with discharge screw and level- Size
- 200 m³ · 7.6 t each
- No.
- 4bin
- Total weight
- 30.2 t
- Rate(estimated)
- Amount
- ₨ 15,172,216
Bagging and stitching line
Weigh, fill, stitch and convey
Rate from 1,600 kg + 5 days labour — Weigher, bagger, stitcher and conveyor- Size
- 4,750 kg/h
- No.
- 2line
- Total weight
- —
- Rate(estimated)
- Amount
- ₨ 1,305,000
Material
₨ 89,294,049
137.2 t of steel to fabricate
Labour
₨ 340,000
136 days at ₨ 2,500 a day
Quotation total
₨ 89,634,050PKR
13 of 13 lines priced
137.16 t is fabricated steel only. 10 bought-in lines — pumps, machines, proprietary units — are priced but carry no steel weight of ours, and show a dash in the weight column.